DONGWON vina factory
07/06/2020
Construction M&E of DONGWON vina Factory Add: Tienson IP Tiendu Dict Bacninh Province Items: Mechanical and Electrical work Schedule: From 08/2018 to 11/2018
Factory VT ASSA ABLOY
07/06/2020
Construction M&E of ASSA ABLOY Factory Add: Bathien 2, Bathien Binhxuyen Vinhphuc Items: Mechanical and Electrical work Schedule: From 01/2020 to 04/2020
Primetech Factory Project
05/06/2020
Construction M&E of PRIME VIETNAM Factory Add: Que vo 3 IP, Que Vo, Bac Ninh, Viet nam Items: Mechanical and Electrical work Schedule: From 12/2019 to 04/2020
Latest quotes for dry transformers 2020
04/07/2019
Quotation of latest 2020 dry transformer from diencongnghiep.top. Find out the 2 most common types of dry transformers available today.